Condor Update 23.11.2017

Halifax

The Salterhebble Hill job is going well, there was a problem last Wednesday night as our site generator was stolen from site which caused a days lost production while a replacement generator was brought to site.

 

The photos show the nailed and meshed face with Towel Rails installed.

Scout Road

Our Condor operators are all undergoing the necessary safety training for the Scout road project. We are hoping to mobilise onto that job next week.

Other opportunities

Condor is looking at 2-3 other projects in the North of England and Wales that hopefully will develop into good solid contracts.

Condor SW

The development of Condor SW is proceeding on schedule. We have had excellent response to advertisements for graduate engineers and interviews will be held later this month.

 

 