Condor Update 26.05.17

Work is continuing on the Breheny Project in Southampton with the main section of Soil Nailing now in full production. After successfully completing the critical areas before the 15th May deadline all efforts are now concentrated on completing the contract. A second rig has now been brought into use to work alongside the TEI rig mounted on a 20T Excavator whilst the second crew are installing nails up to 21m with the Giraffa Rig. Production is high whilst the conditions (apart from the heat) are favourable.