Turner Rise – Colchester.

The end is in sight of this interesting and challenging project

With soil nails being installed at a rate of 25 per day, the forward team stripping down the gabion facing have been kept on their toes. It remains to be seen if the third crew who have commenced meshing put some pressure on the drilling crew. 400+ soil nails have now been installed between 7m and 10m and despite having to contend with delivery wagons to this busy retail park. It looks like time deadlines are on course to be achieved.