University of Birmingham cont’d

Work is continuing on the failed section of wall and river bank at the University of Birmingham.

The reinstatement works have started on the river bank after the wall was rebuilt and anchors installed.

Last week, we continued filling and regrading the river bank. Meshing and fencing started this week in order to complete the project.

The project will be completed within budget and has also been completed in 1 phase as opposed to 2 phases which was originally planned. This saved on additional mobilisation costs and also means the river bank is stabilised for the winter ahead.